Status: 12/1/06
| 2002-2005 | In response to FCET vision for a cohesive environment:
|
| May, 2005 | Recommendation from FCET to ITPB for a Common Environment |
| November, 2005 | Executive Sponsors endorse recommendation ITPB endorses "work plan to select a shared framework for UCLA" Executive Sponsors ask OIT to oversee full review process |
| January, 2006 | Create Functional and Technical Sponsor Groups (Appendix 1) to define principles, summarize needs and develop use cases |
| June, 2006 | Sponsor groups present joint report (Appendix
2) to the FCET
|
| July, 2006 | Create CCLE Assessment Taskforce (Appendix
4) to
|
| August, 2006 |
|
| October 13, 2006 |
|
| October 30, 2006 | Final CCLE Assessment Taskforce provided to FCET |
| November 1, 2006 | Progress report to ITPB |
| November 3, 2006 | At this meeting, the FCET made the following decisions:
|
| November 14, 2006 | CCLE Business Plan Workgroup (Davies, Hernandez, Ryan, Sabean) established to develop plan for presentation to CITI |
| November 20, 2006 | OIT/ATS makes Moodle experimental site available |
| November 28, 2006 | Discussion with Common Systems Group |
| December 1, 2006 | Project Oversight Group hosts discussion with UCLA technical community,
creates CCLE public information site CCLE Executive Sponsors meet with Chancellor |
| December 4, 2006 | Discussion with IT Planning Board |
| December 8, 2006 | FCET discusses "opt-in" position statement and details expectations for UCLA continued engagement with the higher education community. |
| December 2006: |
|
| January 2007: |
|
If funding for 2006-2007 is made available:
| Winter Quarter 07 | Implement experimental (test) CCLE service, begin recruitment of CCLE
staff, select early adopter units |
| Spring Quarter 07 | Alpha service for early adopter units |
| Summer 07 | Beta service for early adopter units; Sakai pilot service ends |
| Fall 07 | Phase I Production service for early adopter units |
Appendix 1: Functional and Technical Sponsor Group membership
Appendix 2: Executive Summary of Joint Report
Appendix 3: Sakai Pilot Sponsors Overview of the Sakai Pilot
Appendix 4: Assessment Taskforce membership
Appendix 5: Project Oversight Group membership